Alvin Dunn School K8 Conversion

Project Overview

Current Project Scope

  • Conversion from Elementary to K-8 International Baccalaureate
  • Phase 1 (Building B): 14 classrooms
  • Phase 2 (Building A): Administration building/35 classrooms
  • Phase 3 (Building C): Multipurpose room/gym, kitchen, locker facilities, band facilities
  • Removal of all buildings/portables
  • Parking lot
  • Bus drop-off
  • Total square feet: 102,000
  • Funding Source: Prop K 
  • Budget: $17M
  • Expenditures: $16.7M  (as of 2-28-19)
  • Rename school to La Mirada Academy (2018-19)

PROJECT STATUS:

  • Phase 1  100% complete
  • Phase 2  100% complete
  • Phase 3   completion August 2019