Alvin Dunn School K8 Conversion


Project Overview

Current Project Scope

  • Conversion from Elementary to K-8 International Baccalaureate
  • 14 classroom and administration building
  • Removal of portable buildings
  • Locker facilities
  • Administration conversion
  • Multipurpose room/gym
  • kitchen expansion
  • New parking lot and student drop-off
  • total square fee: 32,000
  • Funding Source: Prop K
  • Budget: $17M
  • Expenditures: $13.7M

PROJECT STATUS:

  • Phase 1 75% COMPLETE
  • Phase 2 45% complete
  • Phase 3 in design