Alvin Dunn School K8 Conversion

    Project Overview

    Current Project Scope

    • Conversion from Elementary to K-8 International Baccalaureate
    • Phase 1 (Building B): 14 classrooms
    • Phase 2 (Building A): Administration building/35 classrooms
    • Phase 3 (Building C): Multipurpose room/gym, kitchen, locker facilities, band facilities
    • Removal of all buildings/portables
    • Parking lot
    • Bus drop-off
    • Total square feet: 102,000
    • Funding Source: Prop K 
    • Budget: $17M
    • Expenditures: $16.7M  (as of 2-28-19)
    • Rename school to La Mirada Academy (2018-19)

    PROJECT STATUS:

    • Phase 1  100% complete
    • Phase 2  100% complete
    • Phase 3  100% complete