Current Projects

  • Knob Hill Reconstruction
  • Woodland Park Middle Renovation 
  • Transportation Yard Solar & EV Charging Stations Phase II
  • San Marcos High School Sitewide Athletic Improvements

Knob Hill Elementary School

Construction Photos

 

Bldg D: Classrooms/Maker Space/Library - April 2026

Bldg D: Classrooms/Maker Space/Library - April 2026

Bldg D: Classrooms/Maker Space/Library - April 2026

Bldg D: Classrooms/Maker Space/Library - April 2026

Bldg C: Classrooms/Support Spaces/Food Services - April 2026

Bldg C: Classrooms/Support Spaces/Food Services - April 2026

TK Bldg - April 2026

TK Bldg - April 2026

April 2026

April 2026

March 2026

March 2026

December 2025

December 2025

November 2025

November 2025

September 2025

September 2025

Knob Hill Elementary School Reconstruction Project

Project Scope:

  • Reconstruction of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings

Contractor: Balfour Beaty Construction Co.

Architect: DLR Group

Budget: $94M  – Measure JJ

Construction: Phase II Nov 2025 – December 2026

Woodland Park Middle School

Construction Photos

 

Science/Classroom Building - April '26

Science/Classroom Building - April '26

Rooftop Science/Classroom Building - April '26

Rooftop Science/Classroom Building - April '26

Interior Science/Classroom Building - April '26

Interior Science/Classroom Building - April '26

4-28-26

4-28-26

3-24-26

3-24-26

2-23-26

2-23-26

1-15-26

1-15-26

 11-12-25

11-12-25

10-9-25

10-9-25

Woodland Park Middle School Renovation 

Project Scope:

  • Renovation of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings

Contractor: Lusardi Construction Co.

Architect: HMC Architects

Budget: $105.2M - Measure JJ and multiple funding sources

Construction: Began September 26, 2025 for Phase I to include removal of portables 505/506, add temp power, and begin construction on Building H.

Transportation Yard Solar & EV Charging Stations Phase II

 

Project Scope: 

  • Installation of additonal solar power arrays and EV charging stations to promote sustainable transportation and reduce emissions for our electric bus fleet. Phase II

Contractor: Opterra Energy Services, LLC

Budget: $12.8 Million

Construction: Began October 2025

Construction Photos

April 2026

April 2026

April 2026

April 2026

April 2026

April 2026

San Marcos High School Sitewide Athletic Improvements

 

San Marcos High School Sitewide Athletic Improvements 

Project Scope:

  • Stadium: Replacement of artificial turf, including the “D” area. Replacement of synthetic track, shot put area, pole vault, and long jump runways.
  • Multipurpose Fields: Replacement of grass fields with artificial turf and installation of field lights.
  • Beach Volleyball Courts: Addition of three (3) beach volleyball courts.

 

Budget: $7.0M - Measure JJ and CFD

Contractor: C.W. Driver LLC

Construction: May 18, 2026 – October 2026

Stadium

Stadium and Track

Multi-Purpose Fields

Multi purpose field