Current Projects

  • Knob Hill Reconstruction
  • Woodland Park Middle Renovation 
  • Transportation Yard Solar & EV Charging Stations Phase II
  • San Marcos High School Sitewide Athletic Improvements

Knob Hill Elementary School

Construction Photos

 

Building D - Sept '26

Building D - Sept '26

Building C - Sept '26

Building C - Sept '26

Kinder Playground - Sept '26

Kinder Playground - Sept '26

August 2026

August 2026

July 2026

July 2026

April 2026

April 2026

December 2025

December 2025

September 2025

September 2025

Knob Hill Elementary School Reconstruction Project

Project Scope:

  • Reconstruction of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings

Contractor: Balfour Beaty Construction Co.

Architect: DLR Group

Budget: $94M  – Measure JJ

Construction: Phase II Nov 2025 – December 2026

  • Construct Classroom Building E and H
  • Modernize Buildings: B, D1-D4, Admin, PAC/Band
  • Sitework at Buildings A, B, D1-D4, E, and Parking Lots

Woodland Park Middle School

Construction Photos

 

9-28-26

9-28-26

9-28-26

9-28-26

7-29-26

7-29-26

4-28-26

4-28-26

1-15-26

1-15-26

10-9-25

10-9-25

Woodland Park Middle School Renovation 

Project Scope:

  • Renovation of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings

Contractor: Lusardi Construction Co.

Architect: HMC Architects

Budget: $105.2M - Measure JJ and multiple funding sources

Construction: Phase II:  May 2026 – August 2027

  • Demo classrooms 105, 106, 309 & 310
  • Construction of Buildings H & E
  • Modernization of Buildings A/Admin, B/PAC and Band, and D1-D4
  • Sitework at A, B, D1-D4, E and Parking Lots

Transportation Yard Solar & EV Charging Stations Phase II

 

Project Scope: 

  • Installation of additonal solar power arrays and EV charging stations to promote sustainable transportation and reduce emissions for our electric bus fleet. 

Contractor: OPTERRA Energy Services, LLC (formerly ENGIE Services U.S., Inc.)

Budget: $12.8 Million

Construction: Began October 2025

Construction Photos: September 2026

San Marcos High School Sitewide Athletic Improvements

 

San Marcos High School Sitewide Athletic Improvements 

Project Scope:

  • Stadium: Replacement of artificial turf, including the “D” area. Replacement of synthetic track, shot put area, pole vault, and long jump runways. “Complete”
  • Multipurpose Fields: Replacement of grass fields with artificial turf and installation of field lights
  • Beach Volleyball Courts: Addition of three (3) beach volleyball courts
  • Tennis Courts: Resurface “Complete”

 

Budget: $7M - Measure JJ and CFD

Contractor: C.W. Driver LLC

Architect: tBP Architecture

Construction: May 18, 2026 – October 2026

 

Construction Photos