Measure JJ Current Projects
-
Knob Hill Elementary School Reconstruction
Project Scope:
- Reconstruction of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings and associated site work.
Contractor: Balfour Beatty Construction Co.
Architect: DLR Group
Budget: $94M Measure JJ and multiple funding sources
Construction: Began Summer 2025
Estimated Completion Date: August 2028
July 2026:

Food Service Building
Classrooms, Support, and Library Buildings
TK Building

TK/Kinder Driveway
-
Woodland Park Middle School Renovation
Project Scope:
- Renovation of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings, and associated site work.
Contractor: Lusardi Construction Co.
Architect: HMC Architects
Budget: $105.2M - Measure JJ and multiple funding sources
Construction: Began September 26, 2025
Estimated Completion Date: August 2028
- Phase Interim Housing “Onsite”: May ‘26 – Aug ‘26
- Interim Housing “On Site”
- Demo and remodel
- 6th grade “Satellite Campus” at SMMS for the 2026/27 school year
July 2026

New Building H/Science and Classrooms
Admin Building Renovation
Interim Housing -
San Marcos High School Sitewide Athletic Improvements Project
Project Scope:
- Stadium: Replacement of artificial turf, including the “D” area. Replacement of synthetic track, shot put area, pole vault, and long jump runways.
- Multi-Purpose Fields: Replacement of grass fields with artificial turf and installation of field lights.
- Beach Volleyball Courts: Addition of three (3) beach volleyball courts.
- Tennis Courts: Resurface
Budget: $12M - Measure JJ and CFD Funds
Contractor: C.W. Driver, LLC
Architect: tBP/Architecture
Construction: Began May 2026
Estimated Completion Date: December 2026
July 2026
Stadium and Track
Tennis Courts Resurface
Multi-Purpose Fields
Beach Volleyball